Installation of heat supply system was started on the site of Multipurpose Sea Cargo Complex (MSCC) Bronka (Big Port Saint-Petersburg) container and RoRo terminal. Four-pipe heat supply system total installation length exceeds 2500 meters. Completion of construction works August 2015.[ Read more ]

2015-04-14

Installation of water treatment equipment was started on the site of Multifunctional Sea Cargo Complex (MSCC) Bronka (Big Port Saint-Petersburg). Sewage biological treatment during the port operation will be performed with application of advanced membrane treatment MBR (membrane bioreactor) techn[ Read more ]

2015-04-07

FENIX LLC has ordered a special vehicle Mercedes Benz Unimog 400 for provision of fast and safe mooring operations. The vehicle will be equipped with a front power take-off shaft and hydraulic unit. This unique vehicle will allow mooring of vessels at the Port Br[ Read more ]

2015-04-01

Construction of transport detailed examination building was started on the site of Multifunctional Sea Cargo Complex (MSCC) Bronka (Big Port Saint-Petersburg).Part of the building area will be reserved for inspection and temporary storage of detained cargo.Total area of the building will be equal[ Read more ]

2015-03-23

Reefer yard construction has been started on the site of Multifunctional Sea Cargo Complex (MSCC) Bronka (Big Port Saint-Petersburg). Initially the reefer yard will be equipped with 777 power outlets, and will occupy an area of 2.4 ha. In future the number of power outlets will be increased up to[ Read more ]

2015-03-12

Construction works of a warehouse have been started on the site of Multifunctional Sea Cargo Complex (MSCC) Bronka (Big Port Saint-Petersburg). The heated A class 10000 m2 area warehouse is located on the territory of MSCC Bronka container terminal and will be used for temporary cargo storage, st[ Read more ]

2015-03-10

Fenix LLC has placed an order for delivery of handling equipment for MSCC Bronka Ro-ro Terminal (1 fork-lift loader Konecranes SMV 33-1200 with lifting capacity 33 t and 1 fork-lift loader SMV 10-1200 with lifting capacity 10 t). The fork-lift loader Konecranes SMV 33-1200 was specially designed[ Read more ]

2015-02-24

Fenix LLC has signed a contract for delivery of a complex solution for management and automation of MSCC Bronka container terminal operations. The supplier is SOLVO Ltd., a leading industry expert in development and implementation of such solutions in compliance with the existing world standards[ Read more ]

2015-02-20

Fenix LLC has finalized a contract for delivery of 2 Kone SMV 4545?CX5 reach-stackers (rail-stackers), one reach-stacker for container and one for ro-ro terminal of MSCC Bronka. The equipment is fitted out with retractable two-celled telescopic boom and telescopic top spreader with maximal stacki[ Read more ]

2015-02-19

According to the information from BaltStroy CJSC the general contractor for dredging works in the water area and approach channel of the Multifunctional Sea Cargo Complex (MSCC) Bronka (Big Port of Saint-Petersburg) a subcontract for the works to be performed in 2015 was concluded with the la[ Read more ]